Project Description: This project includes a sidewalk along the east side of Grey Road, from Concord Road to Wolfe Street. The sidewalk will link Grey Road property owners and the St. Albans neighborhood to Concord Road, and then to downtown Davidson.
Project Status: Construction bids are due February 5, 2021.
Page Updated: 01/27/2021
TASK | DURATION (DAYS) | COMPLETION DATE |
Complete final design | Tuesday, December 15, 2020 | |
Construction bids due | Friday, February 5, 2021 | |
Award contract | 14 | Friday, February 19, 2021 |
Construction start | 14 | Friday, March 5, 2021 |
Construction complete | 90 | Thursday, June 3, 2021 |
Town of Davidson
Doug Wright, Project Manager
Consultant
Dewberry