Project Status
The master plan application was denied on April 17, 2020 due to outstanding issues. Crescent Acquisitions, LLC has appealed the town's decision to the Board of Adjustment. Please see the Davidson Board of Adjustment webpage for more information.
Recent Update
April 2019: The court ordered that town staff fulfill the project’s outstanding process requirements as soon as possible. This included receiving comments from the Planning Board (April 29, 2019) and holding a Public Input Session (May 2, 2019).
March/April 2020: The project team submitted revised documents in late March. Mecklenburg County and Town of Davidson staff reviewed the documents. See the Documents tab for a copy of the most recent plans, dated 3/24/2020. On April 17, 2020 Town of Davidson staff denied the master plan application due to outstanding issues.
Site Info
- Planning Area: Village Infill (Orange Overlay)
- Project Address: 513 Potts Street
- Parcel ID: 00320511, 00324101
- Acres: 15.01
- Building(s) Count and Type: 247 multifamily units
- Development Description: Crescent Acquisitions, LLC proposes to develop a 15.441± acre site(s) located on Potts Street in Davidson, North Carolina, to accommodate the construction of 250 multi-family residences. The development will also include public open space including a neighborhood park, dog park, and a multi-use path.
- Developer: Crescent Communities, LLC
Project Timeline
- April 2020: On April 17, 2020 Town of Davidson staff denied the master plan application due to outstanding issues.
- Fall 2019 - Spring 2020: The project team submitted multiple sets of revised documents from October to March. Mecklenburg County and Town of Davidson staff reviewed the documents and noted outstanding issues.
- April 2019: The court ordered that town fulfill the project’s outstanding process requirements as soon as possible. This included receiving comments from the Planning Board (Monday, April 29, 2019) and holding a Public Input Session (Thursday, May 2, 2019).
- Fall 2018: A lawsuit was filed by Davidson Acquisition Company, LLC and Crescent Communities, LLC in October 2018.
- August 2018: The Davidson Board of Commissioners denied approval of sewer extension to the proposal.
- Winter 2017 - Summer 2018: Various site plans and revisions were undertaken by the project team in response to Town of Davidson and Mecklenburg County review comments.
- Summer - Fall 2017: Transportation Impact Analysis conducted and report produced.
- May 2017: Master Plan application submitted to Town of Davidson, Mecklenburg County.
Documents
Planning Board Documents
- Potts St. Residential - Staff Analysis
- Potts St. Residential - Technical Review Report [i.e. Staff Review Comments]
- Potts St. Residential - Public Input Session Report [with Town of Davidson Comments]
- Potts St. Residential - TIA Letter
- Potts St. Residential - TIA Summary of Recommendations
Master Plan Documents
- Master Plan - Application
- Master Plan - Site Survey
- Master Plan - Version 1 (05/22/17)
- Master Plan - Version 2 (07/31/17)
- Master Plan - Version 3 (10/26/17)
- Master Plan - Version 4 (04/25/18)
- Master Plan - Version 5 (07/5/18
- Master Plan - Version 6 (10/24/19)
- Master Plan - Version 7 (12/30/19)
- Master Plan - Version 8 (2/13/2020)
- Master Plan - Version 9 (3/24/2020) [CURRENT]
- Master Plan - Building Elevations
- Master Plan - Jurisdictional Wetland Delineation Report and Cultural Resource Assessment
- Post-Construction Ordinance Stream Exemption Letter - Mecklenburg County
- Transportation Impact Analysis (TIA) - Report (12/12/17) [DRAFT]
- Transportation Impact Analysis (TIA) - Report Appendix (12/22/2018) [DRAFT]
Contact
Developer Contact InformationMichael Tubridy (Crescent Communities)
227 W Trade St, Suite 1000
Charlotte, NC 28202
980-321-6247
MTubridy@crescentcommunities.com
Town of Davidson Project Manager
Jason Burdette
Planning Director
Phone: (704) 940-9621
Email: jburdette@townofdavidson.org