Hoke Master Plan

Recent Updates

Overview:  On March 23, 2020 the Town of Davidson received a complete Master Plan application. The proposal proceeded through the master plan process outlined in Section 14.6 of the Davidson Planning Ordinance, including completion of a Transportation Impact Analysis, Public Input Session, and Planning Board review/comment. The plan was approved in April 2021. 

Fall 2022:  The project continues with construction. Stormwater structures are slated for installation in November 2022. The project team is currently working to finalize the park/open space plans based on public engagement conducted in September 2021. Additionally, in accordance with the approved plan the project is purusing annexation for the portion of Catawba Ave. along the project's street frontage. This is so that the required street improvements can be made by the developer and maintained by the Town of Davidson. Questions or comments about construction issues can be sent to the development team’s representatives Mike Tidwell (MTidwell@taylormorrison.com) or Griffin Query (GQuery@taylormorrison.com) or Town of Davidson staff (Doug Wright, dwright@townofdavidson.org).

For information about the affordable housing units at this development, please click here.

  1. Site Info
  2. Timeline
  3. Documents
  4. Contact

Site Info

  • Planning Area: Lakeshore, Village Infill
  • Project Location: 347 Jetton St.
  • Parcel IDs: Main Parcel 00324306; Ancillary Parcels 00324301, 00324303, 00324304, 00324305, 00321103, 00321112
  • Acres: + 5.55
  • Project Description:  The project proposes 81 townhomes (including eight affordable units) fronting Jetton St. and Catawba Ave. as well as internal public spaces. Additionally, the plan proposes a new street connecting Jetton St. and Catawba Ave. along with alleys, two greens and walkways throughout the development. 
  • Developer: Alliance Group and Taylor Morrison Homes